@ -26,6 +26,6 @@
- The are some confussion. We have to give all the report for the MoH and the regional health bureau, not only the MoH (it was what we thought). They lost a lot of infrastructure in the health centers, so we're asking us for some donations from the NGOs in the region to support. We have 10% of the total budget about monitoring, so maybe we can change the monitoring to give them things. It depends, is it legal? if they're not doing monitoring and evaluation, how can we prove that we've worked there for 2 years?
- We need someone once per month to ask them and tell them what we're doing. Paco's office is receiving part of the money from the project. That's pretty much his role.
- MS: How can this be solved?
- AA: His accountant knows the program but is very shy. Someone working close to his accountant, who knows the basic things about the project. Train someone to understand what we're doing and choose someone how can defend the project in the MoH. But now we cannot send Melaku.
- AA: His accountant knows the program but is very shy. Someone working close to his accountant, who knows the basic things about the project. Train someone to understand what we're doing and choose someone how can defend the project in the MoH. But now we cannot send Melaku. allí fue su logista a defender nuestro proyecto y fue una cagada muy gorda. en el mail que recibí del MoH no tenía nada que ver con lo que habíamos hablado. Su cuestión era 'cuando va a ser la reunión del master plan'? y se metió ahí en un lío en el que no tenía que haberse metido.
- ### Decisiones
-